Vox Vertical Village - Work status - July 2019 - Werk Property Group

This month, our building reached the 5th floor, with over 60% of the construction being completed. This means we are one step close to giving you your dream home.

In the past months, the formwork, reinforcement and concreting work up to the 4th floor were completed. We are now at level 5, where we continue the diaphragm concreting work. At this level, the piling of the pillars has already been completed.

The metal structure for floors 1-4 has also been completed while the metal structure for floors 5-9 is supplied and is to be installed during the construction progress.

Our colleagues on the site also work on perimeter fillings from the basement, which are 60% completed.